Rehabilitation of Sewer Network Project of area 701
Rehabilitation of Sewer Network Project of area 701
The project was referred in 2021 with a -12month execution period during which the project was implemented according to the required specifications, utilizing the company›s machinery and workforce exclusively, under the supervision of the resident engineer and within the required time frame. The project serves the Al-Qadha neighborhood in New Baghdad, consisting of two main transmission lines connected to the main Baghdad sewage line, branching out into pipelines with a diameter of 250 mm to manage the sewege from residential floors.
Year2021Scope of workRoad & Infrastructure WorksClientCapital MunicipalityContract statusMain contractorShare